Industrial Installation
Customer:
German industrial equipment manufacturer and system supplier of intelligent machine and line concepts for the production of web products such as wallpaper, floor coverings, film/foils and technical textiles.
Project:
Installation of production line for PVC-expanded leather in Changzhou.
Date:
Jun to Sep 2015
Scope of work:
- Unloading and move-in of all delivered machinery
- Unpacking and disposal of waste packing material
- Positioning of all components according to the layout
- Erection and installation of the steel platform
- Detailed mechanical assembly
- Installation of air ducts
- Installation of cable trays and ducts, cable pulling
- Connection of cables
- Delivery and installation of piping systems for:
- compressed air
- cooling water (incl. Armaflex insulation)
- steam (insulation with Rockwool and gal. metal sheet), incl. x-ray test and documentation
Scope of supply:
- Approx. 6500 hours of mechanical and electrical works
- Divers forklifts, mobile cranes, working platforms
- Fully equipped tool container, other tools
- All materials for the piping systems, incl. installation materials and consumables
Remarks:
The second production line in Zhangjiagang was contracted with SINOSERV as well and successfully installed until February 2016